KAMPALA: The National Water and Sewerage Corporation (NWSC) has launched a six-month programme to improve water supply in Kampala and surrounding areas, targeting households that currently receive water for less than 12 hours a day.
The programme, dubbed Kampala Water Forward-Looking and Optimisation of Water Supply (K-FLOWS), will run from November 2026 to April 2027 and cover Kampala City and serviced areas of Wakiso and Mukono districts.
It follows a Water Supply Reliability Assessment conducted by NWSC in October 2026, which found that some customers receive water for fewer than six hours a day, despite the corporation having sufficient production capacity.
NWSC Managing Director Dr Eng Silver Mugisha said the main challenge was no longer producing enough water but ensuring that available water reaches consumers reliably.
“Our challenge is not simply to produce more water, but to ensure that the water within our systems reaches customers reliably, equitably and sustainably,” Mugisha said during the programme’s launch in Kampala on Thursday.
He said the corporation would shift its focus from measuring infrastructure investments to assessing the actual number of hours customers receive water.
The assessment found that supply constraints were largely caused by inadequate bulk transmission infrastructure, pumping and storage bottlenecks, undersized pipes, water leaks and disruptions associated with ongoing road construction.
NWSC said treatment plants at Ggaba and Katosi have sufficient capacity to meet demand, but weaknesses in the distribution network prevent some communities from accessing the available water.
Under K-FLOWS, the corporation will implement two major interventions: increasing bulk water supply to underserved areas and improving existing distribution networks.
The bulk supply component will involve water transfers between supply zones, network interconnections, pumping upgrades, construction of boreholes and installation of targeted pipelines.
The distribution component will focus on reinforcing existing networks, adjusting supply zones, managing pressure, repairing valves and reducing leakages. The interventions are expected to release about 9,370 cubic metres of water daily for distribution.
NWSC has set a target of increasing supply for customers currently receiving water for less than 12 hours to at least 12 hours daily, with some areas expected to receive between 18 and 24 hours of supply where technically possible.
The corporation says the improvements will be implemented without reducing supply to areas that already receive reliable services.
The first interventions, expected to be completed by December 2026, include the Katosi-Mutungo Water Supply Stabilisation Project and the Ggaba III-Muyenga Bypass.
The two projects are expected to stabilise water supply for approximately 26,842 customer accounts in areas including Rubaga, Lungujja, Makindye, Nateete, Busega, Bulenga, Kakiri and Nansana.
Other interventions scheduled for completion within the six-month period include new boreholes and local water supply schemes in Kikokiro, Kitagobwa, Bukasa, Mengo, Kasenge, Kazinga, Maya, Namungoona and Nalumunye.
NWSC General Manager Kampala Water Eng Mahmood Lutaaya said each intervention would have a designated officer responsible for delivering measurable improvements in the affected communities.
“Every project under the service accelerated programme is tied to a specific problem, a specific community and a specific officer who answers for it,” Lutaaya said.
He said customers would be informed before construction works begin and updated throughout implementation, while complaints would only be closed after physical checks to establish whether water supply had improved.
The corporation will use community meetings, stakeholder engagements, digital platforms and its call centre to communicate planned works and possible interruptions.
K-FLOWS will also run alongside NWSC’s larger Package 2B infrastructure project, which involves installing about 71 kilometres of primary transmission mains, constructing reservoirs at Kanyanya, Kabulengwa and Mutungo, and building booster stations at Kungu and Kabulengwa.
Package 2B is expected to be completed in August 2027.
NWSC says the new six-month programme is intended to provide earlier relief to affected communities while preparing local distribution networks to handle additional water once the larger infrastructure project becomes operational.
The corporation will assess progress through field inspections, customer feedback and monitoring of actual water supply hours in targeted areas